How Much Gravel Do I Need? Cubic Yards, Tons and Waste
Work out how much gravel a driveway or path needs in cubic yards and tons, add the right waste allowance, and round up to a delivery load. Worked example included.
November 24, 2026 · 8 min read

Photo by Ta nya on Pexels
Quick answer: multiply the length and width of the area in feet, multiply by the depth in feet, then divide by 27 to get cubic yards. Multiply cubic yards by the density of your material to get tons, because most suppliers quote gravel by the ton. Add a waste and compaction allowance, usually 10% to 15%, before you order, and round up to the supplier's delivery step.
Why gravel orders go wrong
Gravel is sold two ways: by volume, in cubic yards, and by weight, in tons. A driveway is a volume problem, but the delivery ticket is a weight problem. The bridge between them is density, and density depends on the stone. Work out only the volume and you can end up with a load that is too small, or a quote that is priced by the ton when you thought you were buying by the yard.
The formula, step by step
- Measure the length and width in feet. For an irregular shape, split it into rectangles, work out each one, and add them.
- Convert the depth to feet by dividing inches by 12. Four inches is 0.333 feet.
- Multiply length × width × depth to get cubic feet.
- Divide cubic feet by 27, because a cubic yard holds 27 cubic feet, to get cubic yards.
- Add your waste allowance to the cubic yards.
- Multiply by the material's density in tons per cubic yard to get tons, then round up to the supplier's increment.
Worked example: a 20 by 12 foot driveway at 4 inches
Take a driveway 20 feet long and 12 feet wide, laid 4 inches deep in crushed stone. JobPlumb's gravel calculator runs the same formula, with a default density of 1.4 tons per cubic yard for crushed stone. Using those inputs, the working is:
- Volume: 20 × 12 × (4 ÷ 12) = 80 cubic feet.
- Cubic yards: 80 ÷ 27 = 2.96 cubic yards.
- Tons, no waste: 2.96 x 1.4 = 4.15 tons.
- Cubic yards with 10% waste: 2.96 × 1.10 = 3.26 cubic yards.
- Tons with 10% waste: 3.26 × 1.4 = 4.56 tons.
The calculator does not add waste for you, so the 10% step is yours to add. Applying it to the volume first keeps the figure in cubic yards, which is the number most suppliers will quote back to you, so you can check it before you accept a price.
| Material | Density (tons per cu yd) | Tons, no waste | Tons, 10% waste |
|---|---|---|---|
| Crushed stone | 1.40 | 4.15 | 4.56 |
| Pea gravel | 1.35 | 4.00 | 4.40 |
| Sand | 1.35 | 4.00 | 4.40 |
| Topsoil | 1.10 | 3.26 | 3.59 |
Does the material change the answer?
Yes. The volume stays the same, but the tonnage depends on what the stone weighs. The same 2.96 cubic yards is 4.15 tons of crushed stone and 3.26 tons of topsoil, so ordering by the ton against a yard-based estimate can leave you with the wrong amount. Contractor guides commonly put crushed stone at roughly 1.35 to 1.5 tons per cubic yard, with the figure depending on stone type, size and moisture. A contractor's guide to the weight of crushed stone sets out the range, and Gambrick's conversion guide shows the same conversion in reverse.
Treat the calculator's densities as close estimates, not quotes. Ask the supplier which density they use, and whether their ton figure is short tons or metric tonnes, because a tonne is a different weight again.
Waste, compaction and loose versus settled volume
Gravel arrives loose and settles once it is spread and rolled. The depth you enter should be the finished depth you want, but the order has to cover the settling as well as the waste from spillage, uneven ground and the edges of the area. Guides commonly suggest a 10% to 15% allowance on top of the geometric volume, and more on a long, narrow or uneven run. Hakaru's gravel calculator guide covers the same allowance and why it is a rule of thumb rather than a measurement.
Ground that is soft under the gravel can also take material into it, which no volume calculation can see. If the subgrade is poor, a larger allowance is cheaper than a second delivery.
Working out the order from the supplier's quote
Suppliers sell gravel by the cubic yard, by the ton, or in bulk bags, and quotes do not always say which volume basis they use. Before you order, check three things: the unit on the quote, whether the volume is loose or compacted, and whether there is a minimum load or a short-load fee. A short load often costs more per ton than a full one, so it is usually cheaper to round up to a full delivery than to pay for two.
Where does this fit into a takeoff?
For one driveway, a calculator is enough. On a plan with several areas, the same numbers come from traced areas on a calibrated scale, which is what a digital takeoff does. If you are new to measuring from drawings, what a construction takeoff is explains the steps, and how to calculate square footage covers the area step that feeds the gravel formula. The same volume logic, with a different density, is used for a slab in our guide to how much concrete you need.
A checklist before you order
- Dimensions: length and width measured on site, with irregular areas split into rectangles.
- Depth: the finished depth you want, converted to feet.
- Material: the density your supplier uses, not only a default.
- Allowance: 10% to 15% added to the cubic yards before converting to tons.
- Delivery: rounded up to the supplier's increment, with minimum-load and short-load fees checked.
JobPlumb's free gravel calculator runs this formula with the densities above. Change the depth or the material and the cubic yards and tons update straight away, so you can test the order before you ring a supplier.
Start freeWhere to go next
If you are also pouring concrete, how much concrete do i need uses the same cubic-yard logic with the thickness and bag-yield questions added. If you price the job after measuring, how to price a service job shows how to turn the quantity into a quote.
Frequently asked questions
How many tons of gravel is a cubic yard?
For crushed stone, contractor guides commonly give about 1.35 to 1.5 tons per cubic yard. JobPlumb's calculator uses 1.4 for crushed stone and 1.35 for pea gravel and sand. Confirm the figure with your supplier, because stone type and moisture change it.
How much gravel do I need for a 10 by 20 foot driveway at 3 inches?
10 × 20 × (3 ÷ 12) is 50 cubic feet, which is 1.85 cubic yards. At 1.4 tons per cubic yard that is 2.59 tons. With 10% waste it is 2.04 cubic yards, or 2.85 tons of crushed stone.
How deep should a gravel driveway be?
Depth is a design choice rather than a formula. It depends on the base, the vehicles that will use the drive and the soil underneath. The calculator takes any depth you enter, so use the depth your design calls for.
Is a gravel calculator accurate?
The geometry is exact: length, width and depth give the volume. The densities and waste allowance are estimates. A calculator gets you close enough to order, but the supplier's density and a short-load check decide what you actually pay.